Raise The Roof
The crew has been busy today pre-assembling the roof sections that will be raised into place this week.
Rink 1: Cement Floor Footings Completed
April 29, 2016 by essgbUnderground Plumbing
State DCAMM permits and approvals finally in place … check. Steel set around perimeter for erection this week … check. Underground plumbing for rink #2 progressing … check. Everything Ice / John Burley providing us with awesome site photos … check!
Steel Building Has Arrived
April 15, 2016 by essgbFoundation Footings Continue
January 4, 2016 by essgbFoundation Forms Being Assembled
The forms are set and ready for concrete for about 60% of the turf facility.
Foundation Footings Begin
December 2, 2015 by essgbSports facility developer agrees to pay town
MIDDLETON — The developer of a planned sports facility at Essex Technical High School has agreed to make an annual “in lieu of taxes” payment to the town of Middleton, according to Assistant Town Administrator Ryan Ferrara. Ferrara said the amount has yet to be determined, but one estimate by town officials put the figure […]
3D Renderings Released